Gantt Charts and Timelines

Plan a robot build with a Mermaid Gantt chart, and tell the story of a project with a timeline

By Kevin McAleer,    5 Minutes


Planning a build

Robot builds have a habit of taking longer than expected, usually because one thing depends on another. You can’t test the motors until the chassis is printed, and you can’t print the chassis until it’s designed. A Gantt chart shows each task as a bar along a calendar, so you can see what depends on what and when it’ll all be done.


Your first Gantt chart

gantt
    title SMARS robot build
    dateFormat YYYY-MM-DD
    section Design
        Sketch ideas          :done,   sketch, 2026-11-02, 2d
        Model in Fusion 360   :active, model, after sketch, 4d
    section Build
        3D print parts        :print, after model, 3d
        Assemble and wire     :wire, after print, 2d
    section Code
        Write motor code      :code, after model, 4d
        Test and tweak        :test, after wire, 3d
    Robot finished!           :milestone, after test, 0d

Here’s what it draws:

gantt
    title SMARS robot build
    dateFormat YYYY-MM-DD
    section Design
        Sketch ideas          :done,   sketch, 2026-11-02, 2d
        Model in Fusion 360   :active, model, after sketch, 4d
    section Build
        3D print parts        :print, after model, 3d
        Assemble and wire     :wire, after print, 2d
    section Code
        Write motor code      :code, after model, 4d
        Test and tweak        :test, after wire, 3d
    Robot finished!           :milestone, after test, 0d

Let’s break that down:

  • title adds a heading.
  • dateFormat tells Mermaid how you will write dates. YYYY-MM-DD means 2026-11-02.
  • section groups tasks into coloured bands.
  • Each task is Name : details, and the details are separated by commas.

Task details

Details go in this order, and you can leave out the ones you don’t need:

  1. Tags (optional): done, active, crit (critical, shown in red) or milestone
  2. ID (optional): a short name like print, so other tasks can refer to it
  3. Start: a date like 2026-11-02, or after print to start when another task finishes
  4. Length: like 3d for three days, 1w for a week, or 12h for hours, or an end date

Using after is the clever bit. If the design takes longer, change one number and every task after it moves along automatically.


Skipping weekends

If you only build at weekends, or only on weekdays, tell Mermaid to skip some days with excludes:

gantt
    title Weekday evenings only
    dateFormat YYYY-MM-DD
    excludes weekends
    section Electronics
        Solder the Pico board  :solder, 2026-11-06, 2d
        Test the sensors       :crit, after solder, 2d
gantt
    title Weekday evenings only
    dateFormat YYYY-MM-DD
    excludes weekends
    section Electronics
        Solder the Pico board  :solder, 2026-11-06, 2d
        Test the sensors       :crit, after solder, 2d

The soldering starts on a Friday, so the second day of it moves to Monday.


Timelines: telling a story

A Gantt chart looks forward. A timeline looks back, showing what happened when. It’s great for a project’s history in a README, or a “how this robot evolved” section on a blog post.

timeline
    title The life of my robot
    2024 : First version : Cardboard chassis and an Arduino
    2025 : Switched to a Pico : Rewritten in MicroPython
         : Added a distance sensor
    2026 : 3D printed SMARS body : Wi-Fi remote control

Here’s what it draws:

timeline
    title The life of my robot
    2024 : First version : Cardboard chassis and an Arduino
    2025 : Switched to a Pico : Rewritten in MicroPython
         : Added a distance sensor
    2026 : 3D printed SMARS body : Wi-Fi remote control

Each line is period : event, and you can add more events with more colons, or on the next line starting with :. The period doesn’t have to be a date; it can be any text, like Week 1 or Prototype.

You can group periods with section too, just like in a Gantt chart.


Try it yourself

  1. Make a Gantt chart for your next project with at least three sections. Use after so every task depends on another.
  2. Mark the most important task as crit, and finish with a milestone.
  3. Challenge: write a timeline of your own maker journey, from your first project to today.

Common issues

  • Problem: “Invalid date” or the bars are in strange places
  • Solution: Check your dates match dateFormat exactly, such as 2026-11-02 for YYYY-MM-DD
  • Why: Mermaid reads each date using the format you gave it

  • Problem: A task using after doesn’t appear
  • Solution: Check the ID after after matches another task’s ID exactly
  • Why: Mermaid can’t work out a start date for a task that follows something that doesn’t exist

  • Problem: A colon in a task name breaks the chart
  • Solution: Remove the colon from the name, or use a dash instead
  • Why: The first colon separates the task name from its details

Check your understanding

Quick quiz 1 of 3

What does after print do in a Gantt task?

Quick quiz 2 of 3

Which tag makes a task show as critical?

Quick quiz 3 of 3

When would you use a timeline instead of a Gantt chart?


< Previous Next >

You can use the arrows  ← → on your keyboard to navigate between lessons.


What are you looking for?
Watch Videos Get Ideas Learn Something Read a Review Read the Blog Search
... Z Z z